Maui Council approves a sewer backup plan for the new Waikapū school

The mayor can pursue a temporary hookup to the existing Kahului plant if a new treatment plant is still offline when the school opens and the older system has room.

Archive: The existing Wailuku-Kahului wastewater treatment plant and Kanahā Pond in 2014. · Forest and Kim Starr / CC BY 3.0 US
Archive: The existing Wailuku-Kahului wastewater treatment plant and Kanahā Pond in 2014. · Forest and Kim Starr / CC BY 3.0 US

If the new school in Waikapū is ready for students before Central Maui’s new wastewater plant is working, it could send sewage to an older plant in Kahului. The Maui County Council voted Wednesday to authorize that fallback, with no guarantee of space in the existing system.

The council passed Bill 116 on final reading, allowing Mayor Richard Bissen to enter an agreement with the Hawaiʻi School Facilities Authority. The proposed agreement in the council file sets aside a possible 14,500 gallons a day at the Wailuku-Kahului Wastewater Reclamation Facility. Capacity has to be available when the school’s building permit is approved, and Central Maui’s new plant has to be unavailable when the school opens. The authority expects the first phase to open in fall 2031.

The school authority would be responsible for getting wastewater to the county’s system on Waiʻale Road. The proposal relies on a lift station on an adjacent development parcel and anticipates a separate agreement. The temporary allocation would end once the new Central Maui plant, pump station and pressurized sewer line are in service. The vote gives the school project a route through a possible construction delay, while leaving the connection work with the authority.

Maui Now reported that county environmental management director Shayne Agawa told a council committee in October he expected the new plant to be running before the school opens. That makes the older plant a contingency. Families will still have to look to the school project for the opening date and to the county for when the new plant can take sewage.